=+a. (***) Consider Table 14.4 and Figure 14.5. Every week the project continues costs the Courter Corporation
Question:
=+a. (***) Consider Table 14.4 and Figure 14.5. Every week the project continues costs the Courter Corporation an additional $5,000 in lost profits. The quality control manager says she can crash activity H from 3 weeks