=+ACTIVITY DURATION (WEEKS) PREDECESSORS A Consult with engineering 3.5 None B Determine equipment layout 2 None C
Question:
=+ACTIVITY DURATION
(WEEKS) PREDECESSORS A Consult with engineering 3.5 None B Determine equipment layout 2 None C Install equipment 4.5 A, B D Order materials 2 A E Test equipment 2 C F Train employees 3 D, E G Perform pilot runs 2 F H Get OSHA approval 4 E