b. If there are no changes to either item As gross requirements or beginning inventory over the

Question:

b. If there are no changes to either item A’s gross requirements or beginning inventory over the four-week interval, how do you explain changes in the gross requirements for item B observed in part a? How do you explain this situation to the production manager? What impact would such changes in gross requirements for item B have on supplier relations if B is a purchased part?

240 Chapter 6A Advanced MRP