In a material requirements planning (MRP) system, the projected available balance is a. Existing replenishment orders for

Question:

In a material requirements planning (MRP) system, the projected available balance is

a. Existing replenishment orders for the item due at the beginning of each period

b. Anticipated future usage or demand for the item during each period

c. Current and projected inventory status for the item at the end of the period

d. Planned replenishment orders for the item at the beginning of each period

Fantastic news! We've Found the answer you've been seeking!