In which of the following ways does capacity requirements planning (CRP) differ from rough-cut capacity planning techniques?

Question:

In which of the following ways does capacity requirements planning (CRP) differ from rough-cut capacity planning techniques?

I. CRP uses a time-phased approach II. CRP considers service part demand III. CRP considers standard lot sizes

a. I only

b. II only

c. I and II only

d. I, II, and III