Master production scheduling (MPS) and resource planning are a part of which MPC phase? a. Direction setting
Question:
Master production scheduling (MPS) and resource planning are a part of which MPC phase?
a. Direction setting
b. Detailed planning
c. Execution
d. All of the above
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Manufacturing Planning And Control For Supply Chain Management
ISBN: 9780071750318,9780071750325
1st Edition
Authors: F. Robert Jacobs, William Lee Berry, D. Clay Whybark, Thomas E. Vollmann