Which master production scheduling (MPS) approach is most likely to utilize a planning bill of materials? a.

Question:

Which master production scheduling (MPS) approach is most likely to utilize a planning bill of materials?

a. Make-to-order

b. Assemble-to-order

c. Make-to-stock

d. All are equally likely