From lowest to highest, rank the master production scheduling (MPS) approaches according to the need to monitor
Question:
From lowest to highest, rank the master production scheduling (MPS) approaches according to the need to monitor forecast accuracy.
a. Assemble-to-order, make-to-stock, make-to-order
b. Make-to-order, make-to-stock, assemble-to-order
c. Make-to-stock, assemble-to-order, make-to-order
d. Make-to-order, assemble-to-order, make-to-stock