Which of the following is not true? I. Time-phased planning is typically carried out with material requirements

Question:

Which of the following is not true?

I. Time-phased planning is typically carried out with material requirements planning (MRP)

II. Rate-based planning is likely to utilize large batch sizes III. Rate-based planning is common in just-in-time (JIT) systems

a. I only

b. II only

c. III only

d. I and II only

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Manufacturing Planning And Control For Supply Chain Management

ISBN: 9780071750318,9780071750325

1st Edition

Authors: F. Robert Jacobs, William Lee Berry, D. Clay Whybark, Thomas E. Vollmann

Question Posted: