13. You're managing a construction project. You've decomposed work packages into activities, and your client needs a

Question:

13. You're managing a construction project. You've decomposed work packages into activities, and your client needs a duration estimate for each activity that you come up with. Which of the following will you use for this? A. Milestone list B. Activity list C. Critical path analysis D. Project schedule network diagram