Question:

14. You're managing a project, when you and the seller both agree that you need to have the seller add more resources to the project in order to finish on time. The number of resources is written into the contract. What's the BEST way to proceed? A. Your project will be late because you can't change the contract once it's signed B. You need to convince the buyer to sign a new contract C. You need to use the contract change control system to make the change to the contract D. You need to use claims administration to resolve the issue