17. Given the network diagram below, what's the critical path? A. Start-A-B-C-End B. Start-A-E-F-C-End C. Start-A-E-G-H-End D.

Question:

17. Given the network diagram below, what's the critical path? A. Start-A-B-C-End B. Start-A-E-F-C-End C. Start-A-E-G-H-End D. Start-D-G-H-End