2. You check to make sure that you have all of the features developed in your project...
Question:
2. You check to make sure that you have all of the features developed in your project that you had planned when you reach the “feature complete”
milestone. When you find that you are missing one of the planned features, you realize that a new risk has shown up—you missed one of the required features in your functional specification.
Reassessment Audit Technical Performance Measurement Trend Analysis Reserve Analysis