20. You are managing a project with a BAC of $93,000, EV (BCWP) of $51,840, PV (BCWS)...

Question:

20. You are managing a project with a BAC of $93,000, EV (BCWP) of $51,840, PV (BCWS) of $64,800 and AC (ACWP) of $43,200. What is the CPI? A. 1.5 B. 0.8 C. 1.2 D. $9,000