5. You're managing a project to deliver 10,000 units of custom parts to a manufacturer that uses...
Question:
5. You're managing a project to deliver 10,000 units of custom parts to a manufacturer that uses Just In Time management. Which of the following constraints is most important to your client? A. The parts must be delivered on time B. The parts must be delivered in a specific order C. The parts must conform to ISO specifications D. The parts must be packaged separately
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Question Posted: