5. You're managing an industrial design project. You've come up with the complete activity list, created network
Question:
5. You're managing an industrial design project. You've come up with the complete activity list, created network diagrams, assigned resources to each activity, and estimated their durations. What's the next thing that you do? A. Use Rolling Wave Planning to compensate for the fact that you don't have complete information B. Create the schedule C. Consult the project scope statement and perform Activity Sequencing D. Use fast-tracking to reduce the total duration