You are the project manager at an industrial design firm. You expect to spend a total of

Question:

You are the project manager at an industrial design firm. You expect to spend a total of $55,000 on your current project. Your plan calls for six people working on the project eight hours a day, five days a week for four weeks. According to the schedule, your team should have just finished the third week of the project. When review what the team has done so far, you find that they have completed 50% of the work, at a cost of $25,000. Based on this information, calculate the Earned Value numbers:

image text in transcribed

Check all of the following that apply:
The project is ahead of schedule The project is behind schedule You should consider crashing the schedule The project is over budget The project is under budget You should find a way to cut costs Your current project is an $800,000 software development effort, with two teams of programmers that will work for six months, at a total of 10,000 hours. According to the project schedule, your team should be done with 38% of the work.
You find that the project is currently 40% complete. You’ve spent 50% of the budget so far. Calculate these numbers:

image text in transcribed

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Head First PMP

ISBN: 9781449364915

3rd Edition

Authors: Jennifer Greene, Andrew Stellman

Question Posted: