You are the project manager of a medium-size project that is scheduled to take 10 months from
Question:
You are the project manager of a medium-size project that is scheduled to take 10 months from project initiation on September 1st through delivery on June 30th. It is now April 1st, seven months since the project began, and the project is slightly behind schedule, by perhaps a week.
Draw a Gantt chart (you may use the style shown in Figure 3-2 or another Gantt chart style if you prefer). Assume that project phases can overlap.
Data from Figure 3-2
Step by Step Answer:
Related Book For
Introduction To Systems Analysis And Design
ISBN: 9780073402949
1st Edition
Authors: Jeffrey Whitten, Lonnie Bentley
Question Posted: