Shumpert, Inc., entered into a contract that was to take two years to complete, with an estimated
Question:
a. What was the gross profit reported by the percentage of completion method for 2015?
b. After the contract was completed at the end of 2016 at a total cost of $950,000, what was the gross profit reported by the percentage of completion method for 2016?