12. Following are the various activities involved in a project. The cost and time information for these

Question:

12. Following are the various activities involved in a project. The cost and time information for these activities is given below:

image text in transcribed

(a) Draw the PERT network.

(b) Find out the critical path and the expected project completion time.

(c) What is the minimum possible project completion time after crashing the activities involved in the project and the associated cost of completing the project? (MIB, Delhi, 2005)

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: