The data for a PERT network is given in the following table: (i) Draw a network and

Question:

The data for a PERT network is given in the following table:

image text in transcribed

(i) Draw a network and estimate the earliest and latest event times for all nodes and hence derive critical path.
(ii) Estimate the expected duration of the project and corresponding variance.
(iii) What is the probability that the project duration will exceed 60 days?
(iv) What is the chance of completing the project between 45 and 54 days?
(v) What is the probability of completing the project within 30 days? (MBA, Ruhailkhand, 2003)

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: