Question: 15. A small project is having seven activities. The relevant data about these activities is given below: (i) Find out the normal duration and the

15. A small project is having seven activities. The relevant data about these activities is given below:

Activity Dependence Normal Duration (Days) Crash Duration Normal Cost Crash Cost (Days)

(i) Find out the normal duration and the minimum duration.
(ii) What is the percentage increase in cost to complete the project in 21 days?
(CA, November, 1997)

Activity Dependence Normal Duration (Days) Crash Duration Normal Cost Crash Cost (Days) (Rs) (Rs) A 7 5 500 900 B A 4 2 400 600 C A 5 5 500 500 D A 6 4 800 1,000 E B, C 7 4 700 1,000 F C, D G E, F 56 24 800 1,400 4 800 1,600

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Understanding Management Questions!