Question: 15. A small project is having seven activities. The relevant data about these activities is given below: (i) Find out the normal duration and the
15. A small project is having seven activities. The relevant data about these activities is given below:

(i) Find out the normal duration and the minimum duration.
(ii) What is the percentage increase in cost to complete the project in 21 days?
(CA, November, 1997)
Activity Dependence Normal Duration (Days) Crash Duration Normal Cost Crash Cost (Days) (Rs) (Rs) A 7 5 500 900 B A 4 2 400 600 C A 5 5 500 500 D A 6 4 800 1,000 E B, C 7 4 700 1,000 F C, D G E, F 56 24 800 1,400 4 800 1,600
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
