10. A small project consists of seven activities for which the relevant data are given below: (i)...
Question:
10. A small project consists of seven activities for which the relevant data are given below:
(i) Draw the network and find the project completion time.
(ii) Calculate total float for each of the activities.
(iii) Draw the time scaled diagram.