16. Earliest start and completion times of the various activities of a project are obtained by forward
Question:
16. Earliest start and completion times of the various activities of a project are obtained by forward pass calculations while the latest start and completion times are obtained by backward pass calculations. Mark the statement as T (True) or F (False).