8. A refrigeration company has six plants located in different parts of a city. Every Year, it...

Question:

8. A refrigeration company has six plants located in different parts of a city. Every Year, it is necessary for each plant to be completely overhauled. The overhauling is carried out in two stages A and B, and each stage requires a crew of workmen with completely different skills. The work on stage B can start only when stage A has been completed. A plant has to be closed for the entire period of its overhauling The present schedule of the overhaul of the six plants is as follows:

image text in transcribed

(a) Determine the optimal sequence.

(b) If down-time of any of the six plants costs Rs 800 per day for a plant, idle time for crew A costs Rs 250 per day, and idle time for crew B costs Rs 430 per day, which of the two schedules, the present one and the one determined in (a), will be more economical? What are their respective costs?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: