Question: The following data relate to a project: (a) Draw the network, find the critical path and the duration of the project (the minimum as well

The following data relate to a project:

Activity Activity time (Days) Activity cost (Rs) Regular Crash Regular Crash 1-2

(a) Draw the network, find the critical path and the duration of the project (the minimum as well as the regular).

(b) If the project manager wants to reduce the completion time to 25 days, which activities would be required to be crashed and by how much? What shall be the cost involved?

(c) Can this project be completed in 22 days? If not, why? If yes, what is the cost involved?

Activity Activity time (Days) Activity cost (Rs) Regular Crash Regular Crash 1-2 7 6 700 750 1-3 8 6 650 750 2-4 9 7 800 900 2-5 11 8 1,600 1,800 3-5 8 5 750 1,000 3-6 10 7 1,900 2,100 4-7 12 10 1,200 1,300 5-7 13 11 1,300 1,400 6-7 14 10 1,500 1,800

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Understanding Management Questions!