Suppose a body and paint shop Ira s to work on four cars (A, B, C!, and

Question:

Suppose a body and paint shop Ira s to work on four cars (A, B, C!, and D) of a car rental agency. The manager estimated the job times required (in hours) as follows:
Suppose a body and paint shop Ira s to work

Tire body and paint shop each have dedicated workers. A car has to finish body work before it can be painted. Assume that there are no other cars in the shop.
a. The rental agency is in a hurry to get its cars back. In what order should the shop work on tire cars to minimize their make-span?
b. Draw a load/schedule Gantt chart for your sequence in part a, and determine the make- span.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Operations Management

ISBN: 978-0071091428

4th Canadian edition

Authors: William J Stevenson, Mehran Hojati

Question Posted: