Question: Suppose the part in the previous problem is made in very large quantities on a production line in which an automated work handling system is
Suppose the part in the previous problem is made in very large quantities on a production line in which an automated work handling system is used to transfer parts between machines. Transfer time between stations = 15 s. The total time required to set up the entire line is 150 hours. Assume that the operation times at the individual machines remain the same. Determine
(a) Manufacturing lead time for a part coming off the line,
(b) Production rate for operation 3,
(c) Theoretical production rate for the entire production line?
Step by Step Solution
3.46 Rating (159 Votes )
There are 3 Steps involved in it
a MLT 61025 615 min for an average part after production has ac... View full answer