Question: Suppose you have the following information: Demand rate (D) = 750 units per hour Lead time (T) = 40 hours Container capacity (C) = 1,000

Suppose you have the following information:
Demand rate (D) = 750 units per hour
Lead time (T) = 40 hours
Container capacity (C) = 1,000 units
Safety factor (x) = 10% How many kanban production cards are required?
a. 59
b. 28
c. 30
d. 33

Step by Step Solution

3.43 Rating (178 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

tr msoheightsourceauto col msowidthsourceauto br msodataplacementsamecell style0 msonumberformatGene... View full answer