Suppose you have the following information: Demand rate (D) = 750 units per hour Lead time (T)

Question:

Suppose you have the following information:
Demand rate (D) = 750 units per hour
Lead time (T) = 40 hours
Container capacity (C) = 1,000 units
Safety factor (x) = 10% How many kanban production cards are required?
a. 59
b. 28
c. 30
d. 33