The accountants for Polyglaze, Inc., have developed the following information regarding the standard cost and the actual
Question:
Instructions
a. Compute the materials price variance and the materials quantity variance, indicating whether each is favorable or unfavorable. Prepare the journal entry to record the cost of direct materials used during June in the Work in Process account (at standard).
b. Compute the labor rate variance and the labor efficiency variance, indicating whether each is favorable or unfavorable. Prepare the journal entry to record the cost of direct labor used during June in the Work in Process account (at standard).
c. Compute the overhead spending variance and the overhead volume variance, indicating whether each is favorable or unfavorable. Prepare the journal entry to assign overhead cost to production inJune.