Question: The Budd Gear Co. specializes in heat- treating gears for automobile companies. At 8: 00 a. m., when Budds shop opened today, five orders (listed
The Budd Gear Co. specializes in heat- treating gears for automobile companies. At 8: 00 a. m., when Budds shop opened today, five orders (listed in order of arrival) were waiting to be processed.
.png)
a. If the earliest due date rule is used, what sequence should be used?
b. What will be the average job tardiness?
c. What will be the average number of jobs in the system?
d. Would the SPT rule produce better results in terms of jobtardiness?
Per Unit Time in (minutes/unit) 12 Due Date (min. from now) 160 Order Size at Treatment unite) Order 16 180 190 220 10 10
Step by Step Solution
3.43 Rating (169 Votes )
There are 3 Steps involved in it
Given At 800 am when Budds shop opened today five orders listed in order of arrival were waiting to ... View full answer
Get step-by-step solutions from verified subject matter experts
Document Format (1 attachment)
372-B-M-L-O-M (3455).docx
120 KBs Word File