The company signed an $880,000 contract to build an environmentally friendly access trail to South Willow Lake.
Question:
The company uses the percentage-of-completion method of computing revenue from long-term construction contracts. Assume that the company employs the cost-to-cost method of estimating the percentage of completion. Compute the amount of revenue to be recognized in
(1) Year 1,
(2) Year 2,
(3) Year 3.