The comprehensive regional hospital discussed in the section Resource Planning for Service Providers performs bypass surgery at
Question:
BOR Level Lead Time in Days
Level 1..............................1
Level 2..............................1
Level 3..............................1
Level 4..............................2
Level 5..............................1
Level 6..............................2
Level 7..............................1
Total.................................9
The projected number of completed by-pass procedures over the next 15 days is shown in Table 11.21.
Consider three critical resources of nurses, beds, and lab tests that are required at each level of treatment as shown in Table 11.22.
a. Use the above information to calculate the daily resource requirements (similar to gross requirements on a material record) for each resource to treat bypass patients at this regional hospital.
b. What are the 15-day resource requirements to treat both aneurysm patients and bypass patients?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Operations Management Processes and Supply Chains
ISBN: 978-0133872132
11th edition
Authors: Lee J. Krajewski, Manoj K. Malhotra, Larry P. Ritzman
Question Posted: