The costs to manufacture a part using methods A and B are estimated by CA= 10 +

Question:

The costs to manufacture a part using methods A and B are estimated by CA= 10 + 0.8 P and CB = 60 + 0.8 P − 0.005 P2 respectively, where the cost C is in dollars and P is the number of parts. Estimate the breakeven point.