The Dorben Co. uses a standard hour plan with a base wage of $9.00/hour. It hires an
Question:
a) Find the equation of the learning curve?
b) What is the % learning?
c) How long would it take the worker to reach the standard time of 8.0 minutes
d) Assume that the worker tries to improve and earn the incentive pay. What would the worker be paid for the first 20 hours under the standard-hour plan?
e) Assuming that the worker continues to improve his performance, what will he be paid for the full batch of 300 units under the standard-hour plan?
f) What is the unit cost for the first unit made? What is the cost for 300th unit?