The earliest expected finish time for a project is 138 days, and its required completion time is

Question:

The earliest expected finish time for a project is 138 days, and its required completion time is 130 days. What is the probability of completing the project before its required time if σt (the standard deviation of the total distribution of the activities on the longest path) is 6?

Distribution
The word "distribution" has several meanings in the financial world, most of them pertaining to the payment of assets from a fund, account, or individual security to an investor or beneficiary. Retirement account distributions are among the most...
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Successful Project Management

ISBN: 9780324656138

4th Edition

Authors: Jack Gido, Jim Clements

Question Posted: