The following data were obtained from a project to build a pressure vessel. Activity Duration Predecessors A......................6

Question:

The following data were obtained from a project to build a pressure vessel.
Activity Duration Predecessors
A......................6 weeks...........................---
B......................6 weeks...........................---
C......................5 weeks............................B
D.......................4 weeks.......................A, C
E.......................5 weeks............................B
F........................7 weeks..................D, E, G
G.......................4 weeks............................B
H.......................8 weeks............................F
I.........................5 weeks...........................G
J.........................3 weeks............................I
1. Construct a network diagram for the project.
2. Answer the following questions.
a) Calculate the scheduled completion time.
b) Identify the critical path.
c) What is the slack time (float) for activity A?
d) What is the slack time (float) for activity D?
e) What is the slack time (float) for activity E?
f) What is the slack time (float) for activity?
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Essentials of Materials Science and Engineering

ISBN: 978-1111576851

3rd edition

Authors: Donald R. Askeland, Wendelin J. Wright

Question Posted: