The following data were obtained from a project to build a pressure vessel. Activity Duration Predecessors A......................6
Question:
Activity Duration Predecessors
A......................6 weeks...........................---
B......................6 weeks...........................---
C......................5 weeks............................B
D.......................4 weeks.......................A, C
E.......................5 weeks............................B
F........................7 weeks..................D, E, G
G.......................4 weeks............................B
H.......................8 weeks............................F
I.........................5 weeks...........................G
J.........................3 weeks............................I
1. Construct a network diagram for the project.
2. Answer the following questions.
a) Calculate the scheduled completion time.
b) Identify the critical path.
c) What is the slack time (float) for activity A?
d) What is the slack time (float) for activity D?
e) What is the slack time (float) for activity E?
f) What is the slack time (float) for activity?
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Essentials of Materials Science and Engineering
ISBN: 978-1111576851
3rd edition
Authors: Donald R. Askeland, Wendelin J. Wright
Question Posted: