The following is a table of activities associated with a project at Rafay Ishfaqs software firm in

Question:

The following is a table of activities associated with a project at Rafay Ishfaq’s software firm in Chicago, their durations, and what activities each must precede:

PRECEDES DURATION (WEEKS) ACTIMITY A (start) B, C E 4. F(end)

a) Draw an AON diagram of the project, including activity durations.

b) Define the critical path, listing all critical activities in chrono-logical order.

c) What is the project duration (in weeks)?

d) What is the slack (in weeks) associated with any and all non-critical paths through the project?