The following production flow shows Parts O, Q, and T; Subassembly U; and final assembly for Product

Question:

The following production flow shows Parts O, Q, and T; Subassembly U; and final assembly for Product V.

M to N to O

P to Q R to S to T

O and Q to U

U and T to V

N involves a bottleneck operation, and S involves a capacity- constrained resource. Draw the process flow.