The hiring committee made a job offer to Sharon Adams, and she accepted. She will start her
Question:
First, Sharon would meet with human resources to learn about company benefits and policies (3 hours). When that meeting is over, she could handle three tasks at once: she could tour the company offices (4 hours), meet with users (3 hours), and work on the necessary paperwork (2 hours). After the tour and user meetings, she could meet with the IT managers (1 hour). Then, after meeting the IT managers and with all the paperwork completed, she would meet with the entire IT team for a brief introduction (1 hour).
A. Prepare a work breakdown structure showing tasks, durations, and predecessor tasks.
B. Calculate the start and finish date for each task, and determine the critical path.