The lead time for KraftyCity workbenches is 3 weeks, with a standard deviation of 1.2 weeks, and

Question:

The lead time for KraftyCity workbenches is 3 weeks, with a standard deviation of 1.2 weeks, and the average weekly demand is 24, with a standard deviation of 8 work benches. What should the reorder point be if KraftyCity wants to provide a 95% service level?