The planning department of an electronics firm has set up the activities for developing and production of

Question:

The planning department of an electronics firm has set up the activities for developing and production of a new MP3 Player. Given the information below, develop a project network using Microsoft Project. Assume a five-day workweek and the project starts on January 4, 2010.



The planning department of an electronics firm has set up


The project team has requested that you create a network for the project, and determine if the project can be completed in 45weeks.