The procurement process for Li Wholesale Company includes a series of activities that transforms a materials requisition

Question:

The procurement process for Li Wholesale Company includes a series of activities that transforms a materials requisition into a vendor check. The process begins with a request for materials. The requesting department prepares and sends a materials request form to the Purchasing Department. The Purchasing Department then places a request for a quote to vendors. Vendors prepare bids in response to the request for a quote. A vendor is selected based on the lowest bid. A purchase order to the low-bid vendor is prepared. The vendor delivers the materials to the company, whereupon a receiving ticket is prepared. Payment to the vendor is authorized if the materials request form, receiving ticket, and vendor invoice are in agreement. These three documents fail to agree 50% of the time, initiating effort to reconcile the differences. Once the three documents agree, a check is issued. The process can be diagrammed as follows:


The procurement process for Li Wholesale Company includes a seri


An activity analysis indicated the following activity costs with this process:
Preparing materials request ............$ 19,200
Requesting, receiving, and selecting vendor bids .....60,000
Preparing purchase order .............12,000
Preparing receiving ticket ............16,800
Matching M/R, R/T, and invoice ..........24,000
Correcting reconciliation differences .........84,000
Preparing and delivering vendor payment .......24,000
Total process activity cost ............$ 240,000
On average, the process handles 30,000 individual requests for materials that result in 30,000 individual payments to vendors.
Management proposes to improve this process in two ways. First, the Purchasing Department will develop a preapproved vendor list for which orders can be placed without a request for quote. It is expected that this will reduce the need for requesting and receiving vendor bids by 75%. Second, additional training and standardization will be provided to reduce errors introduced into the materials requisition form and receiving tickets. It is expected that this will reduce the number of reconciliation differences from 50% to 20%, over an average of 30,000 payments.
a. Develop a table showing the percent of individual activity cost to the total process cost for the procurement activities.
b. Determine the average total process cost per vendor payment, assuming 30,000 payments.
c. Prepare a table showing the improvements in the activity costs as a result of the changes proposed by management.
d. Estimate the average cost per vendor payment, assuming that the changes proposed by management are enacted for 30,000 totalpayments.

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Managerial Accounting

ISBN: b010ikdqzm

10th Edition

Authors: Carl S. Warren, James M. Reeve, Jonathan E. Duchac

Question Posted: