The table below shows estimates of activity times (weeks) for a project: Suppose that the critical path

Question:

The table below shows estimates of activity times (weeks) for a project:
The table below shows estimates of activity times (weeks) for

Suppose that the critical path is A-C-D-E-G. What is the probability that the project will be completed within
a. 34.5 weeks?
b. 33 weeks?
c. 35 weeks?