Three Bridges, Inc., shows the following overhead information for the current period: Actual overhead incurred . .
Question:
Three Bridges, Inc., shows the following overhead information for the current period:
Actual overhead incurred . . . . . . . . . $638,400 ($182,400 fixed and $456,000 variable)
Budgeted fixed overhead . . . . . . . . . $187,200 (12,000 direct labor-hours budgeted)
Standard variable overhead rate
per direct labor-hour . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . $36
Standard hours allowed for
actual production . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14,000 hours
Actual labor-hours used . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13,200 hours
Required
What are the variable overhead price and efficiency variances and the fixed overhead price variance?
Step by Step Answer:
Fundamentals of Cost Accounting
ISBN: 978-0077398194
3rd Edition
Authors: William Lanen, Shannon Anderson, Michael Maher