Tiana Shar, the controller for Bondi Furniture Company, is in the process of analyzing the overhead costs
Question:
Tiana Shar, the controller for Bondi Furniture Company, is in the process of analyzing the overhead costs br the month of November, She has gathered the following data for the month.
Labor
Direct-labor hours:
Job 77 …………………………………………….. 3,500
Job 78 ……………………………………………. 3,000
Job 79 ……………………………………………. 2,000
Labor costs:
Direct-labor wages ………………………...….. $204,000
Indirect-labor wages ………………………..……… 15,000
Supervisory salaries ………………………..………. 6,000
Material
Inventories, November 1:
Raw material and supplies ……………………….. $10,500
Work in process (job 77) …………………....……… 54,000
Flushed goods ……………………………………...... 112,500
Purchases of raw material and supplies:
Raw material ……………………………………....... $135,000
Supplies (indirect material) …………………… 15,000
Direct material and supplies requisitioned for production:
Job 77 ……………………………………………........... $ 45,000
Jct78 …………………………………………….... 37,500
Job 79 ……………………………………………... 25,500
Supplies (indirect material) ……………... 12,000
Total ……………………………………………..........… $120,000
Other
Building occupancy costs meat, light, depreciation, etc.)
Factory facilities ………………………………....…. $ 6,400
Sales offices …………………………………….. 1,600
Administrative offices ……………………… 1,000
Total ……………………………………………….......... $ 9,000
Production equipment costs:
Power …………………………………………….............. $ 4,100
Repairs and maintenance ………………………… 1,500
Depreciation ……………………………………… 1,500
Other ……………………………………………… 1,000
Total ………………………………………………. $ 8,100
The firm’s job-order costing system uses direct-labor hours (measured at practical capacity) as the cost driver for overhead application. In December of the preceding year. Shar had prepared the following budget for direct-labor and manufacturing-overhead costs for the current year, The plant is theoretically capable of operating at 150,000) direct-labor hours per year. However, Shar estimates that the practical capacity is 120,000 hours in a typical year.
During November, the following jobs were completed:
Job 77 ……………………………………………. Side chairs
Job 78 ……………………………………………. End tables
Required:
Assist Shar by making the following calculations.
1. Calculate the 1, redelerinincd overhead rate for the current year.
2. Calculate the total cost of job 77.
3. Compute the amount of manufacturing overhead applied to job 79 during November.
4 What was the total amount of manufacturing overhead applied during November?
5, Compute the actual manufacturing overhead incurred during November.
6. Calculate the over applied or under applied overhead for November,
Step by Step Answer: