Tiilikainen Oy has prepared a sales budget of 42 000 finished units for a three-month period. The
Question:
Tiilikainen Oy has prepared a sales budget of 42 000 finished units for a three-month period. The company has a stock of 22 000 units of finished goods on hand at 31 December and has a target finished goods stock of 24 000 units at the end of the succeeding quarter.
It takes 3 litres of direct materials to make 1 unit of finished product. The company has a stock of 90 000 litres of direct materials at 31 December and has a target closing stock of 110000 litres.
Required
How many litres of direct materials should be purchased during the 3 months ending 31 March?