Triplent Company solicited bids from several contractors to construct an addition to its office building. The lowest

Question:

Triplent Company solicited bids from several contractors to construct an addition to its office building. The lowest bid received was for $750,000. Triplent Company decided to construct the addition itself at a cost of $590,000. What amount should be recorded in the building account?