Two machines (a grinding machine and a rolling machine) are required to make each of five products

Question:

Two machines (a grinding machine and a rolling machine) are required to make each of five products with the processing time, average lot size, and setup time given in Table 10.13. Each machine is notorious for breaking down frequently; thus, the company wants to maintain a 30 percent capacity cushion. Each machine is available for 12 hours per day, 260 days per year. Deter-mine how many machines of each type are required.