Using the diagram you created in question 3, calculate ES, EF, LS, and LF for each task

Question:

Using the diagram you created in question 3, calculate ES, EF, LS, and LF for each task and the amount of slack. List the tasks that appear on the critical path.
In question 3
Task A, duration 6, dependent on none
Task B, duration 5, dependent on none
Task C, duration 3, dependent on none
Task D, duration 12, dependent on task B and task C
Task E, duration 2, dependent on task A
Task F, duration 5, dependent on task B
Task G, duration 1, dependent on task B
Task H, duration 9, dependent on task E and task F
Task I, duration 7, dependent on task G
Task J, duration 7, dependent on task H
Task K, duration 3, dependent on task I
Task L, duration 5, dependent on task D
Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Methods of IT Project Management

ISBN: 978-1557536631

2nd edition

Authors: Jeffrey Brewer, Kevin Dittman

Question Posted: