Using the diagram you created in question 3, calculate ES, EF, LS, and LF for each task
Question:
In question 3
Task A, duration 6, dependent on none
Task B, duration 5, dependent on none
Task C, duration 3, dependent on none
Task D, duration 12, dependent on task B and task C
Task E, duration 2, dependent on task A
Task F, duration 5, dependent on task B
Task G, duration 1, dependent on task B
Task H, duration 9, dependent on task E and task F
Task I, duration 7, dependent on task G
Task J, duration 7, dependent on task H
Task K, duration 3, dependent on task I
Task L, duration 5, dependent on task D